Usually both of you, half each. The part people get wrong is the process, not the split.

A timber boundary fence running along the edge of a Tasman property

Under the Fencing Act 1978 your neighbour is generally liable for half the cost of an adequate dividing fence. The split is rarely the problem. What catches people out is skipping the formal fencing notice, which is the step that makes the obligation enforceable if your neighbour later refuses to pay.

This comes up on almost every fencing quote, and the answer is simpler than people expect. The cost split is not usually where it goes wrong.

The short version

Under the Fencing Act 1978, your neighbour is generally liable for half the cost of an adequate dividing fence. You do not need their enthusiasm, and you do not need them to like your choice of timber.

What you do need is to follow the process. The obligation is real, but it becomes difficult to enforce if you skipped the step that creates the paper trail.

What “adequate” means

This is the word that does the work, and it is deliberately not a fixed specification. An adequate fence is one that is reasonable in the circumstances, which takes into account things like:

  • Whether the properties are urban or rural
  • The size and use of each property
  • How close the houses sit to the boundary
  • Any covenants on the titles
  • What the existing fence, if there is one, is already doing

The practical effect is that your neighbour is liable for half of a sensible fence, not half of whatever you fancy. If you want something more expensive than adequate, you can usually still have it, but expect to cover the difference.

The step people skip

Here is where it actually goes wrong. Someone has a friendly chat over the fence, the neighbour says “yeah, sounds good”, the fence gets built, and then the invoice arrives and the neighbour has changed their mind or sold the house.

The formal step is a fencing notice. It is a written notice served under the Act which sets out:

  • That it is served under the Fencing Act 1978
  • The names and addresses of both parties
  • The boundary and what you propose to do
  • The type of fence and who will do the work
  • The estimated total cost
  • When you intend to start
  • That if they do not respond within 21 days they are treated as having agreed

It has to be served properly, which means personally or by registered post rather than dropped in the letterbox.

What happens after you serve it

Two outcomes:

They object. They have 21 days to serve a cross-notice setting out what they object to and what they would prefer instead. You negotiate from there. If you cannot agree, fencing disputes go to the Disputes Tribunal.

They do nothing. If no cross-notice comes back inside 21 days, they are generally treated as having agreed to the proposal, cost sharing included.

That second outcome is the whole reason to bother with the notice. Silence counts in your favour, but only if you served something for them to be silent about.

Being realistic about neighbours

All of that is the legal backstop, not the opening move. In practice the fences that go smoothly are the ones where someone knocked on the door first, showed a couple of options and a rough price, and then followed up in writing.

A few things that help:

  • Talk before you serve anything. A notice landing out of nowhere reads as hostile even when it is not meant to be.
  • Offer a choice. People object far less to a fence they helped pick.
  • Put the friendly version in writing anyway. Agreeing by text is not a fencing notice, but it is a lot better than nothing.
  • Remember it moves with the property. If either of you sells mid-process, you are dealing with someone new.

Where to check the detail

I build fences, I am not a lawyer, and the specifics of your boundary may not match the general position. Worth reading before you commit:

What I can help with

I quote the work either way. The cost sharing is between you and your neighbour, but a written quote with a clear scope is usually what a fencing notice gets built around, so it is a sensible first step even if you have not spoken to them yet.

I build new boundary fences, palings, pickets and post and rail, plus repairs, gates and staining across Nelson, Richmond, Motueka and Māpua. Have a look at fencing services, or get a free quote and I will come and measure up.

Worth reading next: Deck repair or replace?, which applies the same logic to the other big timber structure on most properties.

Questions

Frequently asked questions

Does my neighbour have to pay half?

Generally yes, for an adequate dividing fence, under the Fencing Act 1978. Adequate means reasonable for the circumstances, which takes into account things like whether you are urban or rural, the size of the properties and any covenants. If you want something beyond adequate, you can usually still build it, but you may be covering the difference yourself.

What is a fencing notice and do I really need one?

It is a written notice served under the Fencing Act setting out what you propose to do, what it will cost and who will do the work. You do not legally have to serve one to build a fence, but without it you have no straightforward way to make your neighbour contribute. Most disagreements I hear about started with a verbal agreement and no paperwork.

What if my neighbour objects?

They have 21 days from the notice to serve a cross-notice setting out their objection and any counter-proposal. If they do, the two of you negotiate from there. If it cannot be resolved, the Disputes Tribunal handles fencing disagreements.

What if my neighbour just ignores the notice?

If no cross-notice comes back within 21 days, they are generally treated as having agreed to what you proposed, including the cost sharing. That is exactly why the notice matters. Silence works in your favour only if you served one.

Do I need council consent for a boundary fence?

In most cases a residential fence up to 2.5 metres does not need building consent, but there are exceptions, and pool fencing has its own separate rules entirely. Check your specific situation with Tasman District Council before work starts.